- ROADMAP_2026.md: 4 Phases (Phase 1: Shadow Run ~ Phase 4: Operations) - WBS_MASTER.md: 40+ tasks with dependencies (Critical Path: 67-107 days) - STRATEGY_OPTIMAL_EXECUTION.md: AGENTS.md v16.0 20-principle framework Phase Timeline: - Phase 1: 50-90 days (auto-running Job 3227) - Phase 2: 15 days (evidence verification) - Phase 3: 2 days (production deployment) - Phase 4: Continuous (monthly debt paydown 20%) Go-Live Target: 2026-11-20 (Production: kartsell.taxbaik.com) Following AGENTS.md v16.0: - SOLID, Code Refactoring, Data Integrity, No Gold-Plating - Normalization/Denormalization, Process Automation, Standardization - Vibe Coding, Hallucination Prevention, Field Evidence - Reproducibility, Traceability, Stability, Architecture Evolution - Modularity, Right Way, Technical Debt (20% monthly paydown) Co-Authored-By: Claude Haiku 4.5 <noreply@anthropic.com>
219 lines
4.9 KiB
Markdown
219 lines
4.9 KiB
Markdown
# K-ArtSell Aegis v16.0: 완전 배포 로드맵 (2026-08-11 ~ 2026-12-31)
|
|
|
|
## 🎯 최종 목표
|
|
**프로덕션 배포 & 자동 운영 (2026-11-20)**
|
|
|
|
---
|
|
|
|
## 📅 전체 일정 (4 Phases)
|
|
|
|
### Phase 1: Shadow Run (자동 진행 중)
|
|
**기간:** 2026-08-11 ~ 2026-10-31 (50-90일)
|
|
**상태:** 🟢 자동 실행 중 (Job 3227)
|
|
**담당:** Hangfire 자동화
|
|
|
|
**산출물:**
|
|
- ✅ 252+ 트레이딩 데이 검증 (자동)
|
|
- ✅ PBO (Probability of Backtest Overfit) 메트릭
|
|
- ✅ DSR (Daily Sharpe Ratio) 메트릭
|
|
- ✅ OOS (Out-of-Sample) 분석
|
|
- ✅ Crash Recovery 검증 (4/4 시나리오)
|
|
|
|
**진행 상황:**
|
|
```
|
|
08-11: Phase 1 시작
|
|
08-11~10-31: 50-90일 자동 실행
|
|
10-31: 예상 완료 (조정 가능)
|
|
```
|
|
|
|
---
|
|
|
|
### Phase 2: 증거 수집 & 검증 (예상 11-01 ~ 11-15)
|
|
**기간:** ~15일
|
|
**상태:** ⏳ 대기 중 (Phase 1 완료 대기)
|
|
**담당:** 엔지니어링 팀
|
|
|
|
**작업 항목:**
|
|
```
|
|
□ PBO 메트릭 검증 (< 20% threshold)
|
|
□ DSR 메트릭 검증 (> 0.5 threshold)
|
|
□ OOS 드리프트 검증 (< 2.5% threshold)
|
|
□ Crash Recovery 로그 분석
|
|
□ 감시 이벤트 로그 검토 (DEBT-014/029)
|
|
□ 최종 기술부채 검토 (quarterly 20%)
|
|
□ Phase 1 전체 리포트 작성
|
|
```
|
|
|
|
**산출물:**
|
|
- 최종 증거 보고서
|
|
- PBO/DSR/OOS 검증 결과
|
|
- 기술부채 20% 결제 확인
|
|
- Production Sign-Off 문서
|
|
|
|
---
|
|
|
|
### Phase 3: 프로덕션 배포 (2026-11-20 예상)
|
|
**기간:** ~1-2일
|
|
**상태:** ⏳ 대기 중
|
|
**담당:** DevOps + 엔지니어링
|
|
|
|
**배포 작업:**
|
|
```
|
|
□ kartsell.taxbaik.com 배포 준비
|
|
□ 데이터베이스 마이그레이션 (0041 포함)
|
|
□ Environment 설정 (API keys, secrets)
|
|
□ Nginx 설정 (reverse proxy)
|
|
□ SSL 인증서 갱신
|
|
□ 부하 테스트 (sandbox)
|
|
□ Smoke 테스트 (production)
|
|
□ 배포 실행
|
|
□ 배포 후 검증 (모니터링 3일)
|
|
```
|
|
|
|
**산출물:**
|
|
- 배포 체크리스트
|
|
- 배포 후 모니터링 결과
|
|
- 프로덕션 상태 보고서
|
|
|
|
---
|
|
|
|
### Phase 4: 운영 & 모니터링 (2026-11-20 ~ 2026-12-31+)
|
|
**기간:** 무한 (지속 운영)
|
|
**상태:** ⏳ 대기 중
|
|
**담당:** SRE 팀
|
|
|
|
**월별 작업:**
|
|
```
|
|
11월 (배포 후 3주):
|
|
□ 안정성 모니터링 (SLA 99.5%)
|
|
□ 성능 메트릭 수집
|
|
□ 사용자 피드백 수집
|
|
□ 긴급 버그 패치
|
|
|
|
12월:
|
|
□ 기술부채 월별 20% 결제
|
|
□ Q4 성과 리뷰
|
|
□ Q1 2027 계획 수립
|
|
|
|
2027+:
|
|
□ Continuous Deployment
|
|
□ A/B 테스트 (새 모델)
|
|
□ 자동 모델 승격 (threshold 시)
|
|
□ 월별 기술부채 관리
|
|
```
|
|
|
|
**모니터링 항목:**
|
|
```
|
|
□ Model Drift (OOS, PBO, DSR)
|
|
□ Data Quality (duplicate detection, reconciliation)
|
|
□ System Health (99.5% SLA, response time)
|
|
□ Cost Analysis (infrastructure, API usage)
|
|
□ Business Metrics (advisory effectiveness)
|
|
```
|
|
|
|
---
|
|
|
|
## 📊 마일스톤 타임라인
|
|
|
|
```
|
|
2026-08-11
|
|
│
|
|
├─ Phase 1 START (Job 3227)
|
|
│ └─ Automatic execution for 50-90 days
|
|
│
|
|
2026-10-31 (예상)
|
|
│
|
|
├─ Phase 1 COMPLETE
|
|
│ └─ PBO/DSR/OOS evidence ready
|
|
│
|
|
2026-11-01 ~ 11-15
|
|
│
|
|
├─ Phase 2: Evidence Verification
|
|
│ └─ All thresholds verified
|
|
│
|
|
2026-11-20
|
|
│
|
|
├─ Phase 3: PRODUCTION DEPLOYMENT
|
|
│ └─ kartsell.taxbaik.com live
|
|
│
|
|
2026-11-20 ~ 12-31
|
|
│
|
|
└─ Phase 4: Monitoring & Operations
|
|
└─ Monthly debt paydown (20%)
|
|
```
|
|
|
|
---
|
|
|
|
## 🎯 성공 기준
|
|
|
|
| 단계 | 기준 | 검증 방법 |
|
|
|------|------|---------|
|
|
| **Phase 1** | 252+ trading days, all metrics ready | Job 3227 logs |
|
|
| **Phase 2** | PBO<20%, DSR>0.5, OOS<2.5% | Analysis report |
|
|
| **Phase 3** | Deployment successful, 99.5% SLA | Monitoring dashboard |
|
|
| **Phase 4** | Monthly 20% debt paydown, no P1 incidents | Git log, alerts |
|
|
|
|
---
|
|
|
|
## 🚀 의존성 분석
|
|
|
|
```
|
|
Phase 1 (자동)
|
|
↓ (50-90일 자동 실행)
|
|
Phase 2 (증거 수집)
|
|
↓ (검증 완료)
|
|
Phase 3 (배포)
|
|
↓ (배포 성공)
|
|
Phase 4 (운영)
|
|
↓ (지속 진행)
|
|
|
|
병렬화 불가:
|
|
- Phase 1 완료 없이 Phase 2 불가
|
|
- Phase 2 검증 없이 Phase 3 불가
|
|
|
|
빠른 경로 가능:
|
|
- Phase 1 조기 완료 → 배포 앞당김
|
|
```
|
|
|
|
---
|
|
|
|
## ⚠️ 리스크 & 완화 전략
|
|
|
|
| 리스크 | 확률 | 영향 | 완화 |
|
|
|--------|------|------|------|
|
|
| Phase 1 기간 초과 | 중 | 배포 지연 | 주간 진행 모니터링 |
|
|
| PBO 임계값 미충족 | 저 | 배포 불가 | 모델 재조정 계획 |
|
|
| 배포 중 장애 | 저 | 서비스 중단 | 롤백 계획, sandbox 테스트 |
|
|
| 기술부채 누적 | 중 | 유지보수 비용 | 월별 20% 결제 강제 |
|
|
|
|
---
|
|
|
|
## 📋 다음 체크포인트
|
|
|
|
```
|
|
매주 금요일 (또는 필요시):
|
|
- Phase 1 진행률 확인 (Job 3227 로그)
|
|
- 이슈 식별 및 계획 조정
|
|
|
|
2026-10-20 (예상):
|
|
- Phase 1 완료 예측 검증
|
|
- Phase 2 준비 시작 (팀 할당)
|
|
|
|
2026-11-01:
|
|
- Phase 2 공식 시작
|
|
- 증거 수집 병렬화
|
|
|
|
2026-11-15:
|
|
- Phase 3 배포 승인 (또는 지연 결정)
|
|
|
|
2026-11-20:
|
|
- 프로덕션 배포 (또는 재일정)
|
|
```
|
|
|
|
---
|
|
|
|
**Document Version:** 1.0
|
|
**Last Updated:** 2026-08-11
|
|
**Owner:** Engineering Team
|
|
**Status:** ACTIVE
|