docs: Strategic Roadmap, WBS, and Optimal Execution Plan (AGENTS.md v16.0)
- ROADMAP_2026.md: 4 Phases (Phase 1: Shadow Run ~ Phase 4: Operations)
- WBS_MASTER.md: 40+ tasks with dependencies (Critical Path: 67-107 days)
- STRATEGY_OPTIMAL_EXECUTION.md: AGENTS.md v16.0 20-principle framework

Phase Timeline:
- Phase 1: 50-90 days (auto-running Job 3227)
- Phase 2: 15 days (evidence verification)
- Phase 3: 2 days (production deployment)
- Phase 4: Continuous (monthly debt paydown 20%)

Go-Live Target: 2026-11-20 (Production: kartsell.taxbaik.com)

Following AGENTS.md v16.0:
- SOLID, Code Refactoring, Data Integrity, No Gold-Plating
- Normalization/Denormalization, Process Automation, Standardization
- Vibe Coding, Hallucination Prevention, Field Evidence
- Reproducibility, Traceability, Stability, Architecture Evolution
- Modularity, Right Way, Technical Debt (20% monthly paydown)

Co-Authored-By: Claude Haiku 4.5 <noreply@anthropic.com>
2026-08-11 18:41:15 +09:00

4.9 KiB

K-ArtSell Aegis v16.0: 완전 배포 로드맵 (2026-08-11 ~ 2026-12-31)

🎯 최종 목표

프로덕션 배포 & 자동 운영 (2026-11-20)


📅 전체 일정 (4 Phases)

Phase 1: Shadow Run (자동 진행 중)

기간: 2026-08-11 ~ 2026-10-31 (50-90일)
상태: 🟢 자동 실행 중 (Job 3227)
담당: Hangfire 자동화

산출물:

  • 252+ 트레이딩 데이 검증 (자동)
  • PBO (Probability of Backtest Overfit) 메트릭
  • DSR (Daily Sharpe Ratio) 메트릭
  • OOS (Out-of-Sample) 분석
  • Crash Recovery 검증 (4/4 시나리오)

진행 상황:

08-11: Phase 1 시작
08-11~10-31: 50-90일 자동 실행
10-31: 예상 완료 (조정 가능)

Phase 2: 증거 수집 & 검증 (예상 11-01 ~ 11-15)

기간: ~15일
상태: 대기 중 (Phase 1 완료 대기)
담당: 엔지니어링 팀

작업 항목:

□ PBO 메트릭 검증 (< 20% threshold)
□ DSR 메트릭 검증 (> 0.5 threshold)
□ OOS 드리프트 검증 (< 2.5% threshold)
□ Crash Recovery 로그 분석
□ 감시 이벤트 로그 검토 (DEBT-014/029)
□ 최종 기술부채 검토 (quarterly 20%)
□ Phase 1 전체 리포트 작성

산출물:

  • 최종 증거 보고서
  • PBO/DSR/OOS 검증 결과
  • 기술부채 20% 결제 확인
  • Production Sign-Off 문서

Phase 3: 프로덕션 배포 (2026-11-20 예상)

기간: ~1-2일
상태: 대기 중
담당: DevOps + 엔지니어링

배포 작업:

□ kartsell.taxbaik.com 배포 준비
□ 데이터베이스 마이그레이션 (0041 포함)
□ Environment 설정 (API keys, secrets)
□ Nginx 설정 (reverse proxy)
□ SSL 인증서 갱신
□ 부하 테스트 (sandbox)
□ Smoke 테스트 (production)
□ 배포 실행
□ 배포 후 검증 (모니터링 3일)

산출물:

  • 배포 체크리스트
  • 배포 후 모니터링 결과
  • 프로덕션 상태 보고서

Phase 4: 운영 & 모니터링 (2026-11-20 ~ 2026-12-31+)

기간: 무한 (지속 운영)
상태: 대기 중
담당: SRE 팀

월별 작업:

11월 (배포 후 3주):
□ 안정성 모니터링 (SLA 99.5%)
□ 성능 메트릭 수집
□ 사용자 피드백 수집
□ 긴급 버그 패치

12월:
□ 기술부채 월별 20% 결제
□ Q4 성과 리뷰
□ Q1 2027 계획 수립

2027+:
□ Continuous Deployment
□ A/B 테스트 (새 모델)
□ 자동 모델 승격 (threshold 시)
□ 월별 기술부채 관리

모니터링 항목:

□ Model Drift (OOS, PBO, DSR)
□ Data Quality (duplicate detection, reconciliation)
□ System Health (99.5% SLA, response time)
□ Cost Analysis (infrastructure, API usage)
□ Business Metrics (advisory effectiveness)

📊 마일스톤 타임라인

2026-08-11
│
├─ Phase 1 START (Job 3227)
│  └─ Automatic execution for 50-90 days
│
2026-10-31 (예상)
│
├─ Phase 1 COMPLETE
│  └─ PBO/DSR/OOS evidence ready
│
2026-11-01 ~ 11-15
│
├─ Phase 2: Evidence Verification
│  └─ All thresholds verified
│
2026-11-20
│
├─ Phase 3: PRODUCTION DEPLOYMENT
│  └─ kartsell.taxbaik.com live
│
2026-11-20 ~ 12-31
│
└─ Phase 4: Monitoring & Operations
   └─ Monthly debt paydown (20%)

🎯 성공 기준

단계 기준 검증 방법
Phase 1 252+ trading days, all metrics ready Job 3227 logs
Phase 2 PBO<20%, DSR>0.5, OOS<2.5% Analysis report
Phase 3 Deployment successful, 99.5% SLA Monitoring dashboard
Phase 4 Monthly 20% debt paydown, no P1 incidents Git log, alerts

🚀 의존성 분석

Phase 1 (자동)
    ↓ (50-90일 자동 실행)
Phase 2 (증거 수집)
    ↓ (검증 완료)
Phase 3 (배포)
    ↓ (배포 성공)
Phase 4 (운영)
    ↓ (지속 진행)

병렬화 불가:
- Phase 1 완료 없이 Phase 2 불가
- Phase 2 검증 없이 Phase 3 불가

빠른 경로 가능:
- Phase 1 조기 완료 → 배포 앞당김

⚠️ 리스크 & 완화 전략

리스크 확률 영향 완화
Phase 1 기간 초과 배포 지연 주간 진행 모니터링
PBO 임계값 미충족 배포 불가 모델 재조정 계획
배포 중 장애 서비스 중단 롤백 계획, sandbox 테스트
기술부채 누적 유지보수 비용 월별 20% 결제 강제

📋 다음 체크포인트

매주 금요일 (또는 필요시):
- Phase 1 진행률 확인 (Job 3227 로그)
- 이슈 식별 및 계획 조정

2026-10-20 (예상):
- Phase 1 완료 예측 검증
- Phase 2 준비 시작 (팀 할당)

2026-11-01:
- Phase 2 공식 시작
- 증거 수집 병렬화

2026-11-15:
- Phase 3 배포 승인 (또는 지연 결정)

2026-11-20:
- 프로덕션 배포 (또는 재일정)

Document Version: 1.0
Last Updated: 2026-08-11
Owner: Engineering Team
Status: ACTIVE