kjh2064 53be11673c docs: correct WBS tracker and roadmap against verified current state
Both docs were stale relative to 115 commits already on main (VS-03
Approval Workflow, VS-04 Audit Trail, AEG-X-009 live API integration,
Phase 3 J/K/L Sell Decision/Trade Execution/Portfolio Reconciliation),
and repeated an already-corrected false claim that Phase 1 shadow run
was RUNNING.

WBS_PROGRESS_TRACKER.csv:
- AEG-VS-03-01, AEG-VS-04-01: PLANNED/BLOCKED -> COMPLETED, with real
  file paths, commit refs, and isolated test-run counts (20/20, 5/5)
  as evidence.
- AEG-VS-10-01: BLOCKED -> COMPLETED (implementation), with an
  explicit caveat that PBO/DSR production validation is separate and
  still blocked on Phase 1 - not overclaiming past what's verified.
- Added AEG-VS-12-01 (Trade Execution) and AEG-VS-14-01 (Portfolio
  Reconciliation), which had no tracker row at all despite being
  merged to main.
- Flagged a real WBS_ID collision: WBS_MASTER.csv defines VS-03/04/12/14
  as different, unrelated slices (IngestMarketDataPIT, ApplyCorporateActions,
  RankBuyCandidates, GenerateDailyRecommendations). Per user decision,
  kept the tracker's existing IDs and recorded the collision as
  DECISION_REQUIRED on each affected row rather than silently
  renumbering or picking a side.
- Softened AEG-VS-05-01/AEG-X-011/AEG-VS-09-01/AEG-VS-19-01 notes that
  implied Phase 1 was actively counting down ("Job 976, ~50-90 days") -
  corrected to say Phase 1 has not been queued.
- Re-confirmed PHASE-1-SHADOW-RUN unchanged: still no RunId/JobId
  anywhere in this workspace.

CURRENT_ROADMAP.md: full rewrite. Dropped the 2026-08-03 snapshot
content, replaced with what's actually true today, and added a short
"how to re-verify this document" section (check git log divergence,
re-run tests in isolation not just as a full suite, confirm file paths
before writing COMPLETED) aimed at whoever updates this next.

Co-Authored-By: Claude Haiku 4.5 <noreply@anthropic.com>
2026-08-07 23:45:07 +09:00
..