4e87c05a63
Complete system-level work breakdown structure (6 work packages): - WP1: Phase 0 Foundation (6h, blocking) - WP2: Phase 1 Contracts (3h, blocking) - WP3: Phase 2 Frontend (6h, parallelizable at T+0) - WP4: Phase 2 Backend (6h, sequential after Phase 1 at T+9h) - WP5: Phase 3 Features & QA (4h) - WP6: Phase 4 Deployment (2h) Parallelization savings: ~9-10 hours wall clock time Timeline: 21 hours actual (vs 30+ hours sequential) Resource allocation scenarios: - Team of 2 sequential: 21h each = 3 days - Team of 2 parallelized: 19h each, 21h wall clock Critical path analysis with dependency map AGENTS.md v16.0 13/13 compliance checklist Co-Authored-By: Claude Haiku 4.5 <noreply@anthropic.com>