3 parallel workstreams (J/K/L):
- J: VS-10 Sell Decision Engine (4-5 weeks)
- K: VS-12 Trade Execution System (3-4 weeks)
- L: VS-14 Portfolio Reconciliation (2-3 weeks)

Execution model: Parallel + Phase 1 concurrent
Time saved: 4 weeks (vs sequential approach)
AGENTS.md v16.0: 13/13 compliance framework

Team allocation: 8 people, ~450 hours total
Timeline: 2026-09-05 start, 2026-10-16 ready for Gate 2
Production: November 2026 deployment

Co-Authored-By: Claude Haiku 4.5 <noreply@anthropic.com>
2026-08-07 17:31:40 +09:00

17 KiB

Phase 3 Implementation Plan: Sell Decision + Trade Execution

Date: 2026-08-07
Status: 📋 PLANNING (Ready for execution)
Execution Model: WBS Optimization (Parallel + Phase 1 concurrent)
Compliance: AGENTS.md v16.0 13/13 criteria


📊 PHASE 3 OVERVIEW

Context

Phase 1:  🚀 Shadow Run (autonomous, 50-90 days, data generating)
Phase 2:  ✅ Complete (10 PRs merged, code integrated)
Phase 3:  📋 Ready to plan (use Phase 1 data → decisions → execution)
Phase 4:  🔮 Advanced (post-Phase 1, Gate 2+ prerequisites)

Phase 3 Goals

1️⃣  Sell Decision Engine
    → Generate sell signals based on model recommendations
    → Implement approval workflow integration
    → Enforce PBO/DSR validation gates

2️⃣  Trade Execution System
    → Execute approved sell decisions
    → Handle KIS API integration
    → Track execution lifecycle

3️⃣  Portfolio Reconciliation
    → Verify execution vs. approval
    → Update holdings & cost basis
    → Generate reconciliation reports

Key Dependencies

Blockers:   Phase 1 must provide OOS/PBO/DSR evidence ✅ (autonomous)
Ready Now:  Phase 2 infrastructure (approval/audit) ✅ (merged)
New Work:   VS-10 (Sell Decision), VS-05+ (advanced features)

🎯 PHASE 3 WORKSTREAMS

WORKSTREAM J: VS-10 Sell Decision Engine

Owner: Quant Lead + PM
Duration: 4-5 weeks
Start: 2026-09-05 (after Phase 1 reaches 50% progress)
Blocks: VS-12, VS-13 (downstream)

Deliverables

J1: Data Contract & Slice Spec

  • Document: VS-10-SLICE_SPEC.md (300-400 lines)
  • Inputs: Model recommendations, PBO/DSR scores, OOS validation
  • Outputs: Sell decision (quantity, timing, exit strategy)
  • State Machine:
    PENDING (awaiting Phase 1 evidence)
    ↓
    SIGNAL_GENERATED (model consensus)
    ↓
    PBO_VALIDATED (score check ≥ threshold)
    ↓
    DSR_VALIDATED (ratio check ≥ threshold)
    ↓
    OOS_APPROVED (out-of-sample performance confirmed)
    ↓
    READY_FOR_APPROVAL (meets governance gates)
    ↓
    APPROVED (maker-checker approval from VS-03)
    ↓
    EXECUTED (trade sent to KIS)
    ↓
    CONFIRMED (settlement confirmed)
    

J2: Sell Priority Logic

  • Immutable Sell Priority: HARD_IMPAIRMENT → PORTFOLIO_SURVIVAL → DYNAMIC_PROFIT_FLOOR → CONCENTRATION/LIQUIDITY → OPPORTUNITY_COST → REENTRY_OPTION
  • Algorithm: Score-based ranking (fairness + compliance)
  • Output: Ordered list of candidates for execution

J3: API Endpoints (3)

POST /sell-decisions
  Input: model_id, threshold_pbo, threshold_dsr
  Output: 201 Created with decision_id

GET /sell-decisions
  Query: status, model_id, execution_date
  Output: Paginated list

POST /sell-decisions/{id}/execute
  Input: approval_id (from VS-03)
  Output: 202 Accepted (job queued)

J4: Database Schema

CREATE TABLE sell_decisions (
  id UUID PRIMARY KEY,
  model_id UUID REFERENCES models(id),
  status VARCHAR(50),  -- PENDING, SIGNAL_GENERATED, PBO_VALIDATED, ..., CONFIRMED
  pbo_score DECIMAL(5,4),
  dsr_metric DECIMAL(5,4),
  oos_performance JSONB,
  sell_priority INT,
  target_quantity INT,
  target_price DECIMAL(15,2),
  approval_id UUID REFERENCES approval_proposals(id),
  execution_id UUID,  -- Reference to KIS trade
  published_at TIMESTAMPTZ,
  correlation_id UUID,
  revision INT
);

CREATE TABLE sell_decision_evidence (
  id UUID PRIMARY KEY,
  decision_id UUID REFERENCES sell_decisions(id),
  evidence_type VARCHAR(50),  -- PBO_REPORT, OOS_BACKTEST, DSR_METRIC
  evidence_url TEXT,
  validated_at TIMESTAMPTZ,
  published_at TIMESTAMPTZ,
  correlation_id UUID
);

J5: Handlers & Jobs

  • GenerateSellDecisionHandler — Orchestrates scoring + validation
  • ValidatePboHandler — PBO score gate (≥ 0.65 recommended)
  • ValidateDsrHandler — DSR ratio gate (≥ 0.015 recommended)
  • ValidateOosHandler — OOS performance gate (pass/fail)
  • ExecuteSellDecisionJob — Queues trade via KIS API

J6: Tests

  • 15+ unit tests (scoring logic, validation gates, priority ranking)
  • 8+ integration tests (E2E from signal to approval)
  • 3+ contract tests (approval/audit integration)

J7: Compliance

  • AGENTS.md 13/13 (SOLID, complexity, audit, necessity, etc.)
  • PIT tracking (published_at, correlation_id, revision)
  • Immutable decisions (INSERT-only, no UPDATE)
  • Evidence linkage (S3 artifacts)

WORKSTREAM K: VS-12 Trade Execution

Owner: Backend Lead + Trading Ops
Duration: 3-4 weeks
Start: 2026-09-10 (parallel with J, overlapping)
Depends On: J (sell decision approval)

Deliverables

K1: KIS API Integration

  • Service: KisTradeExecutionService.cs
  • Methods:
    ExecuteTradeAsync(tradeRequest, correlationId)
    GetOrderStatusAsync(orderId)
    CancelOrderAsync(orderId, reason)
    ConfirmSettlementAsync(orderId)
    
  • Features:
    • Connection pooling + retry logic (exponential backoff)
    • Order validation (quantity, price, liquidity checks)
    • Failure classification (transient/permanent/liquidity)

K2: Trade Lifecycle States

PENDING (awaiting execution)
↓
SUBMITTED (sent to KIS)
↓
ACCEPTED (KIS confirmed receipt)
↓
PARTIAL_FILLED / FILLED (execution progress)
↓
CONFIRMED (settlement confirmed)
↓
RECONCILED (cost basis updated)

K3: API Endpoints (2)

POST /trades
  Input: sell_decision_id, quantity, limit_price
  Output: 202 Accepted with trade_id

GET /trades
  Query: status, decision_id, execution_date
  Output: Paginated list with execution details

K4: Database Schema

CREATE TABLE trades (
  id UUID PRIMARY KEY,
  sell_decision_id UUID REFERENCES sell_decisions(id),
  kis_order_id VARCHAR(50),  -- KIS-assigned order ID
  status VARCHAR(50),  -- PENDING, SUBMITTED, ACCEPTED, FILLED, CONFIRMED, RECONCILED
  quantity INT,
  executed_quantity INT,
  unit_price DECIMAL(15,2),
  total_amount DECIMAL(18,2),
  commission DECIMAL(15,2),
  net_proceeds DECIMAL(18,2),
  execution_timestamp TIMESTAMPTZ,
  settlement_timestamp TIMESTAMPTZ,
  error_message TEXT,
  kis_response JSONB,
  published_at TIMESTAMPTZ,
  correlation_id UUID,
  revision INT
);

K5: Handlers & Jobs

  • SubmitTradeHandler — Submit to KIS
  • PollTradeStatusJob — Hangfire polling (q-evaluation queue)
  • ConfirmSettlementHandler — Mark settlement complete
  • ReconcileTradeHandler — Update cost basis

K6: Tests

  • 12+ unit tests (validation, state transitions)
  • 8+ integration tests (KIS mock + real DB)
  • 3+ failure scenario tests (transient/permanent errors)

K7: Compliance

  • AGENTS.md 13/13
  • Idempotent execution (no duplicate trades)
  • Audit trail (all state changes logged)
  • Error classification

WORKSTREAM L: VS-14 Portfolio Reconciliation

Owner: Data Architecture + Finance
Duration: 2-3 weeks
Start: 2026-09-15 (parallel with K, uses K output)
Depends On: K (trade execution)

Deliverables

L1: Reconciliation Engine

  • Algorithm: Compare approved decisions vs. executed trades
  • Inputs:
    • Sell decision (approved, PBO/DSR/OOS validated)
    • Trade execution (settled, cost basis confirmed)
    • Holdings (before execution)
  • Outputs:
    • Holdings updated
    • Cost basis adjusted
    • Reconciliation report (matches/mismatches)

L2: Mismatch Detection

  • Quantity mismatch (approved vs. executed)
  • Price variance (approved limit vs. actual)
  • Timing variance (decision date vs. execution date)
  • Settlement delay (execution vs. confirmation)

L3: Cost Basis Update

  • Weighted average cost tracking
  • Lot tracking (FIFO/LIFO methods)
  • Gain/loss calculation
  • Tax lot reporting

L4: API Endpoints (2)

GET /reconciliation/holdings
  Response: Current portfolio state (updated after trade)

GET /reconciliation/mismatches
  Query: date_range, severity
  Response: Flagged discrepancies for manual review

L5: Database Schema

CREATE TABLE holdings (
  id UUID PRIMARY KEY,
  security_id UUID REFERENCES financial_security_master.securities(id),
  quantity INT,
  weighted_avg_cost DECIMAL(15,2),
  total_cost_basis DECIMAL(18,2),
  market_value DECIMAL(18,2),
  unrealized_gain_loss DECIMAL(18,2),
  updated_at TIMESTAMPTZ,
  published_at TIMESTAMPTZ,
  correlation_id UUID,
  revision INT
);

CREATE TABLE reconciliation_logs (
  id UUID PRIMARY KEY,
  trade_id UUID REFERENCES trades(id),
  holding_id UUID REFERENCES holdings(id),
  quantity_before INT,
  quantity_after INT,
  cost_basis_delta DECIMAL(18,2),
  mismatch_detected BOOLEAN,
  mismatch_reason TEXT,
  reconciled_at TIMESTAMPTZ,
  published_at TIMESTAMPTZ,
  correlation_id UUID
);

L6: Tests

  • 10+ unit tests (cost basis, gain/loss calculation)
  • 6+ integration tests (reconciliation workflow)
  • 3+ scenario tests (edge cases: splits, dividends)

📈 EXECUTION TIMELINE

Week 1-2 (2026-09-05 ~ 2026-09-18)

J1: VS-10 Spec & Contract Design (parallel)
K1: VS-12 API & KIS Integration (parallel)
L1: VS-14 Design & Algorithm (parallel)

Status: D/E/F design docs, ready for implementation
Phase 1: 50%-75% progress

Week 3-4 (2026-09-19 ~ 2026-10-02)

J2-J7: VS-10 Implementation & Tests
K2-K6: VS-12 Implementation & Tests
L2-L5: VS-14 Implementation & Tests

Status: All 3 slices in parallel, 50% code complete
Phase 1: 75%-90% progress

Week 5-6 (2026-10-03 ~ 2026-10-16)

J/K/L: Integration testing (cross-slice)
       Phase 1 final results available
       Gate 2 validation begins

Status: All code complete, integration verified
Phase 1: 90-100% (completion), results ready

Week 7+ (2026-10-17+)

Phase 1 Complete → Gate 2 Execution
Phase 3 Implementation → Production Deployment (~November)

🎯 WBS OPTIMIZATION STRATEGY

Parallel Execution (J + K + L Simultaneous)

Sequential (Baseline):  J(4w) → K(3w) → L(2w) = 9 weeks
Parallel (Actual):      All 3 simultaneous = 5 weeks
────────────────────────────────────────────────
TIME SAVED:             4 weeks ⏱️

Dependencies:
  J outputs → K inputs (sell decision → trade execution)
  K outputs → L inputs (trade execution → reconciliation)
  
Overlap Strategy:
  Week 1-2: J design, K design, L design (PARALLEL)
  Week 2-3: J → 50%, K start (J unblocks K)
  Week 3-4: J → 100%, K → 50%, L start (K unblocks L)
  Week 4-5: All 3 at 75-100% (overlapping)
  Week 5-6: Integration testing (all done)

Phase 1 Concurrent Execution

Phase 1:  🚀 Autonomous (50-90 days, data generating)
Phase 3:  📋 Implementation in parallel (uses accumulated data)

Benefit:
  • No waiting for Phase 1 to complete
  • Infrastructure ready when Phase 1 evidence available
  • Gate 2 validation can begin on Day 75+ (mid-way through Phase 1)
  • Production deployment by November 2026

AGENTS.md v16.0 COMPLIANCE PLAN

Verification Framework (Apply to J/K/L)

Criterion J (Sell Decision) K (Trade Execution) L (Reconciliation)
1. SOLID 3 services (scoring, validation, approval) KIS service + handlers Reconciliation + reports
2. Complexity Each <300 lines, readable Connection pool, retry logic Calc engine, mismatch detection
3. Audit correlation_id, PIT tracking All state changes logged Cost basis trail
4. Necessity Grounded in Phase 1 evidence Spec-before-code Portfolio integrity
5. Normalization 3NF schema, append-only PIT tracked decisions Versioned holdings
6. Simplicity State machine clear No magic numbers Algorithm transparent
7. Pattern Vertical Slice (Services/Handlers/Endpoints/Sql) Contract-driven Domain-driven design
8. Guardrails Validation gates (PBO/DSR/OOS) Error classification Mismatch alerts
9. Traceability Evidence links to S3 CorrelationId throughout Audit trail immutable
10. Safety Idempotent operations Rollback-safe state No partial reconciliation
11. Maturity Spec-before-code Data contracts Design docs
12. Right-Way Formal gates, no shortcuts KIS official API Regulatory compliance
13. Debt No new tech debt Enables Phase 4 Tech debt registry

📊 RESOURCE ALLOCATION

Workstream J (Sell Decision) — 3 people, 5 weeks

Lead:     Quant Lead (decision logic, PBO/DSR validation)
Backend:  2 engineers (API, database, handlers, tests)
Effort:   ~200 hours

Workstream K (Trade Execution) — 3 people, 4 weeks

Lead:     Backend Lead (KIS integration, error handling)
Trading:  1 operations engineer (KIS API knowledge)
Backend:  1 engineer (handlers, jobs, reconciliation)
Effort:   ~150 hours

Workstream L (Portfolio Reconciliation) — 2 people, 3 weeks

Lead:     Data Architect (reconciliation algorithm)
Finance:  1 engineer (cost basis, gain/loss, reporting)
Effort:   ~100 hours

Total Phase 3 Effort: ~450 hours (~11 weeks serial, 5 weeks parallel)


📋 MILESTONE CHECKLIST

Phase 3 Gates (Pre-Merge)

J (Sell Decision):

  • VS-10 SLICE_SPEC complete (Spec-before-code)
  • PBO/DSR/OOS validation gates designed
  • API contracts finalized
  • Database migration validated (fresh/upgrade/re-run)
  • Unit tests: 15/15 PASS
  • Integration tests: 8/8 PASS
  • Architecture tests: SOLID compliance verified
  • No SELECT *, schema-qualified SQL
  • Immutable decisions (INSERT-only)
  • Correlation_id traceability

K (Trade Execution):

  • VS-12 SLICE_SPEC complete
  • KIS API contract finalized
  • Error classification (transient/permanent/liquidity)
  • Idempotency key strategy
  • Unit tests: 12/12 PASS
  • Integration tests: 8/8 PASS
  • State machine transitions verified
  • Rollback-safe design confirmed

L (Portfolio Reconciliation):

  • VS-14 SLICE_SPEC complete
  • Reconciliation algorithm validated
  • Cost basis calculations verified
  • Unit tests: 10/10 PASS
  • Integration tests: 6/6 PASS
  • Edge cases (splits, dividends) handled
  • Tax lot tracking verified

Cross-Slice Integration:

  • J → K flow verified (decision → execution)
  • K → L flow verified (execution → reconciliation)
  • Audit trail (VS-04) integration complete
  • Approval workflow (VS-03) integration complete
  • E2E tests: PASS
  • Gate 2 prerequisite data ready (Phase 1 evidence)

🎯 SUCCESS CRITERIA

Code Quality

Tests:      48+ (unit/integration/E2E)
Coverage:   ≥80% code coverage
Complexity: All classes <300 lines
Compliance: AGENTS.md 13/13 ✅
Tech Debt:  No new unbounded debt

Business Metrics

Sell Decision Accuracy:  PBO/DSR/OOS validation pass rate ≥95%
Trade Execution Rate:    Approved decisions → executed ≥99%
Reconciliation Success:  Mismatches ≤0.1% (normal variance)
SLA Compliance:          Execution latency <1 hour (from approval)

Timeline

Week 5-6:    All code merged to main
Week 6-7:    Integration testing & bug fixes
Week 7+:     Production deployment (Gate 2+ validation)
November:    Production live (full automation)

📈 PHASE 3 ROADMAP DIAGRAM

Phase 1 (Autonomous)      Phase 2 (Merged)         Phase 3 (Parallel)
─────────────────        ───────────────          ──────────────────
50-90 days               ✅ Complete              J: Sell Decision  
(Data generating)        10 PRs merged            K: Trade Exec     (Parallel)
                                                  L: Reconciliation 
                                                  
                         VS-03 Approval   ──→  J→K (flow)
                         VS-04 Audit      ──→  all J/K/L logged

                                                  ↓ (Week 6)
                                                  Integration tests
                                                  
                                                  ↓ (Week 7)
                                                  Gate 2 validation
                                                  (Phase 1 evidence)
                                                  
                                                  ↓ (Week 8+)
                                                  Production

APPROVAL & SIGN-OFF

Phase 3 Plan Status: 📋 Ready for review and team assignment
Dependencies: Phase 1 autonomous (no manual action needed)
Readiness: Phase 2 infrastructure (approval/audit) merged
AGENTS.md Compliance: 13/13 criteria framework

Next Steps:

  1. Team review Phase 3 plan
  2. Assign teams to J/K/L workstreams
  3. Start Phase 3 implementation (2026-09-05)
  4. Monitor Phase 1 progress (autonomous)
  5. Execute Phase 3 in parallel with Phase 1 completion

Generated: 2026-08-07
Prepared By: Claude Haiku 4.5 noreply@anthropic.com
Framework: WBS Optimization + AGENTS.md v16.0
Status: READY FOR EXECUTION