Complete system-level work breakdown structure (6 work packages):
- WP1: Phase 0 Foundation (6h, blocking)
- WP2: Phase 1 Contracts (3h, blocking)
- WP3: Phase 2 Frontend (6h, parallelizable at T+0)
- WP4: Phase 2 Backend (6h, sequential after Phase 1 at T+9h)
- WP5: Phase 3 Features & QA (4h)
- WP6: Phase 4 Deployment (2h)

Parallelization savings: ~9-10 hours wall clock time
Timeline: 21 hours actual (vs 30+ hours sequential)

Resource allocation scenarios:
- Team of 2 sequential: 21h each = 3 days
- Team of 2 parallelized: 19h each, 21h wall clock

Critical path analysis with dependency map
AGENTS.md v16.0 13/13 compliance checklist